shapka_top_eng.jpg

Kazakhstan. Shulbinskaya HPP

  • Period of construction 1976-1994;
  • Number of hydroelectric units 6;
  • PJSC Dnipro-SGEM made reconstruction and commissioning of three hydro units;
  • Installed capacity of each hydraulic unit 120 MW;
  • Turbine 50--850;
  • Generator -1636/200-80 ;
  • Turbine wheel diameter 8,5 m;
  • Design head 40 m.

 ,

 ,